(September 26) Here’s the latest information on the construction work scheduled for Red Meadow and Moose Creek roads from Rob Davies, Hungry Horse-Glacier View District Ranger…
I just talked to the Forest Service COR, Cliff Lewis.
The contractor is still working on the 1677 cut-across road towards Red Meadow Road. He is hoping to finish the 1677 Rd this week and then start on the Red Meadow Road on Monday. The Road work on Red Meadow will have delays and is expected to last 2 weeks.
So, at this point, Moose Creek Rd work is expected to start in 2 weeks — approximately Oct 13th.
Once the Moose Cr Road work and culvert replacement gets started, the contractor, and myself, will do our best to communicate what’s going on. There will be an option for emergencies.
If a resident needs to get through for medical reasons or other emergencies they could use the newly refurbished 1677 and cut-across to Red Meadow… then out to the North Fork.
The contractor is Erin Gyman of AGS Inc. He is willing to communicate directly with land owners once he begins work on Moose Cr. Rd.