Here’s the web page for our local road construction project status. It includes some photos and links to a short newsletter that seems to come out about every four weeks:
North Fork of the Flathead River; Blankenship and Belton Stage Rd. Resurfacing.
An update taken from the September 1 project newsletter . . .
On Glacier Drive near Polebridge, clearing, and grubbing activities are complete. Culvert installation is also complete. Once the crew has completed placement of millings on Blankenship & Belton Stage Roads, they will mobilize to Glacier Drive and start placing millings before beginning surface work near Polebridge Mercantile.
On North Fork Road, the contractor’s plan is to start 6-7 day work weeks until project completion. Culvert installation, survey, clearing, and grubbing activities are ongoing.The contractor is scheduled to mobilize the crushing operation and begin processing surface aggregates at Whale Creek Pit in the next week.
For more details, see:
Road construction timing and restrictions revealed at Interlocal